PFAS doesn't care about your program

PFAS doesn't care about your program.

Melbourne found that out the expensive way.

The tunnel that couldn't dig.

In June 2019, PFAS turned up in groundwater samples along the West Gate Tunnel route.

The project was set to excavate around 3 million tonnes of spoil. Tunnelling couldn't start until someone decided where it would go.

Landfill approvals were granted, challenged in the Supreme Court, withdrawn and granted again. A disposal site wasn't chosen until June 2021.

The Victorian Ombudsman found the EPA had to advise on the spoil without knowing the exact PFAS levels, because the testing wasn't enough.

Then came claims for billions in extra cost and a major time extension.

Around two years of mega machines sitting still. Over dirt nobody could prove anything about.

The rules have tightened since.

PFAS NEMP 3.0, the national plan for managing PFAS, was agreed by every Australian environment minister in December 2024 and released in March 2025.

It updates the guidance on stockpiling, reuse of contaminated soil, remediation and landfill disposal.

On the Defence estate, any project likely to disturb soil or water needs a PFAS check, and the project has to fund it.

Translation: "we'll sort it out at the tip" is no longer a plan.

So here's the uncomfortable question.

If the testing is mandatory, why isn't the tracking?

You can have the best lab report in the country. If you can't show where each load went after it left the hole, the report is worth nothing.

Contaminated doesn't have to mean landfill.

NEMP 3.0 includes guidance on reusing PFAS-contaminated soil. Like for like, matched to the same contamination, kept within the site.

But only if you can prove it. Zone by zone. Load by load.

Without that proof, everything gets treated as the worst case. Everything goes to landfill. Everyone pays.

Know before you dig. Prove it after.

Dirt Drop classifies fill from the environmental data you already have, overlays it on a live map and tracks every load from cut to fill.

No guesswork. No dockets. One audit-ready record.

PFAS is called a forever chemical.

The delay shouldn't be forever too.

Could your project prove where every PFAS load went?

Sources

Victorian Ombudsman, Investigation into EPA decisions on West Gate Tunnel Project spoil disposal, May 2022

Department of Climate Change, Energy, the Environment and Water, PFAS National Environmental Management Plan 3.0

SA Environment Protection Authority, Guidance for managing PFAS in SA (NEMP 3.0 agreed December 2024, released 4 March 2025)

Department of Defence, Defence PFAS Construction and Maintenance Framework